OL3 nuclear reactor's startup postponed to September 2019 (Finland)

The Finnish power utility Teollisuuden Voima Oyj (TVO) has provided an updated schedule for the commissioning of the 1,650 MW Olkiluoto-3 (OL3) nuclear power project in Eurajoki (Finland). The fuel will be loaded in January 2019, the reactor will be connected to the national grid in May 2019 (its expected commissioning date) and the power generation start up is now scheduled in September 2019.



The OL3 European Pressurized Reactor (EPR) project is being built by a consortium of Areva GmbH, Areva NP (now Orano) and Siemens under a fixed-price turnkey contract. The project has been hit by repeated delays, court disputes and rising costs. Initially planned to start in 2009, the new reactor will be completed approximately 10 years behind schedule. TVO originally claimed €2.6bn from the Areva-led consortium, which has filed a counter-claim of €3.5bn. In November 2017, TVO received a final and binding partial award under the framework of the ongoing International Chamber of Commerce (ICC) arbitration proceeding. In March 2018, TVO agreed a settlement with Areva-Siemens, which will pay TVO compensation of €450m (the consortium is entitle to receive an "incentive payment" of up to €150m for on time commissioning).

LCOE and CAPEX

Searching for proven generation costs?

Then CAPEX & LCOE is the database you need. The module provides exclusive insights on both Capital Expenditure and Levelised Cost of Electricity.

Make informed decisions in terms of which technologies to invest in and where. In just a few clicks, access unique, premium data on both thermal and renewable power generation costs by technology and by country. Put our detailed, reliable information to use and benchmark your project.

Request a free trial Contact us