Zeevonk (a JV between Vattenfall and Copenhagen Infrastructure Partners) has selected Siemens Gamesa as turbine supplier for Phase I of its Zeevonk offshore wind project in the North Sea, off the coast of the Netherlands (Vattenfall press release, 18/11/2026).
Siemens Gamesa will supply 69 SG 15-236 turbines of 15 MW nominal capacity each for a combined capacity of 1,035 MW. The company will also provide long-term service and maintenance under a separate service and warranty agreement.
The two agreements are the project’s largest contracts and complete the key supplier agreements for the construction phase. Turbine manufacturing is planned for 2028 and installation is targeted for 2029, with commissioning in 2029 too. Phase I remains subject to a final investment decision. Phase II is scheduled for 2032, adding 1 GW of wind capacity and 500 MW of system integration capacity.
Interested in Power Plants?
Enerdata has developed a market research service to screen, monitor and analyse the development of power generation assets.
Power Plant Tracker offers an interactive database and a powerful search engine covering power plants worldwide – including both installed and planned capacities for renewables and fossil fuels.
Energy and Climate Databases
Market Analysis