Squadron Energy has submitted a scoping report for the proposed 1 GW Cullen Bullen BESS in New South Wales (Australia) (Squadron Energy press release, 24/11/2026). The facility would provide up to eight hours of storage and is planned for direct connection to Transgrid’s existing 500 kV transmission network.
The project remains at an early development stage and is expected to be assessed as a State Significant Development. The indicative development schedule anticipates the issue of environmental assessment requirements in 2027, followed by assessment and determination in 2028. An FID could be taken in 2029, with construction potentially beginning in 2030.
If developed at its proposed scale, Cullen Bullen would be among Australia’s largest battery projects. However, the capacity, design, investment decision and construction schedule remain provisional and subject to environmental assessment, regulatory approval and further development work.