PetroVietnam and AES secure key permit for the Son My LNG terminal (Vietnam)

The Vietnamese national oil and gas company PetroVietnam Gas (PV Gas) and AES Corporation have secured an Investment Registration Certificate for the 3.6 Mt/year Son My LNG import terminal in the central province of Binh Thuan (Vietnam). The project’s capacity could be expanded to 9.6 Mt/year at a later stage. Commissioning is scheduled in 2025-2026. The US$1.4bn LNG terminal will receive, process, and supply reprocessed LNG as fuel for the Son My 2 CCGT project (2.2 GW), operated by AES, which should also enter operations in 2025. AES received approval for the power plant project in September 2019; the power plant will have a 20-year contract with the government. In September 2021, the two companies signed a joint venture agreement to establish and operate the project.