GenOn expects to deactivate 3,140 MW of coal-fired generating capacity in PJM between June 2012 and May 2015 because forecasted returns on investments necessary to comply with environmental regulations are insufficient.



The units expected to be deactivated and timeframes are subject to further review based on market conditions. In particular, while the initial analysis for additional environmental controls at Avon Lake indicated that forecasted returns on those investments were insufficient, the evaluation of the returns on those environmental controls is continuing.



Units to be deactivated :












Elrama / PA 460 MW June 2012
Niles / OH 217 MW June 2012
Portland / PA 401 MW January 2015
Avon Lake / OH 732 MW April 2015
New Castle / PA 330 MW April 2015
Shawville / PA 597 MW April 2015
Titus / PA 243 MW April 2015
Glen Gardner / NJ 160 MW May 2015
Power plant tracker

Interested in Power Plants?

Enerdata has developed a market research service to screen, monitor and analyse the development of power generation assets.

Power Plant Tracker offers an interactive database and a powerful search engine covering power plants worldwide – including both installed and planned capacities for renewables and fossil fuels.

Request a free trial Contact us