The Swedish battery storage company Flower has partnered with the project developer dces group to develop the 500 MW/2 GWh Ragow BESS project in Brandenburg, Germany (Flower press release, 16/11/2026).
Under the agreement, dces will oversee project development with support from Flower. Flower, which acquired the project in 2025, will be responsible for financing, EPC, operation and commercialisation of the asset.
The building permit applications of the project have already been submitted, and it is expected to reach ready-to-build status in 2027 with a commissioning targeted for 2029.