The Council of the European Union and the European Parliament have reached a provisional agreement aimed at accelerating permit-granting procedures for electricity grids, renewable energy projects and energy storage facilities (European Council press release, 18/11/2026).
The revised rules seek to tackle delays by establishing clearer deadlines for approving permits and granting grid connections to renewable energy and storage projects. They also introduce specific time limits for authorising new electricity and gas infrastructure, as well as the deployment of recharging stations.
- EU member states will be able to give these projects priority by applying the presumption of an ‘overriding public interest’. However, individual countries may choose not to apply this principle where necessary to protect national security, defence interests or cultural heritage.
- To reduce administrative delays, the agreement also allows member states to consider the absence of a response from the relevant authorities at certain intermediate stages of the permitting process as tacit approval, in line with the Council's position on this matter.
The agreement is still provisional and must be formally approved by both the Council and the European Parliament. Once adopted, member states will have 18 months to incorporate the directive into their national legislation.
The European Commission initially put forward the permitting directive in December 2025, following findings that lengthy and complicated authorisation procedures were holding back the development of energy infrastructure.
Separately, EU MEPs and Council negotiators have agreed to postpone by two years the implementation of requirements obliging oil, gas and coal importers to report methane emissions. The decision comes amid disruptions to energy markets associated with the US-Israeli war with Iran, according to a press release from the European Parliament.
“Under the deal, importers of crude oil, natural gas and coal would have until May 2030, to show that supply contracts concluded or renewed since 4 August 2024 cover only fuel subject to monitoring, reporting and verification measures equivalent to EU rules. The same date would apply when importers report on their efforts to bring older contracts into line”, said the press release.
- In addition, EU producers and importers will be required to disclose the methane intensity of the fossil fuels they supply to the EU market by 5 August 2030, instead of the initially scheduled deadline of 5 August 2029.
- The agreement also grants EU oil and gas operators an additional two years to submit verified reports bringing together source-level and site-level methane measurements. The new deadlines will be 5 February 2029 for operated assets and 5 August 2030 for non-operated assets.
Interested in Global Energy Research?
Enerdata's premium online information service provides up-to-date market reports on 110+ countries. The reports include valuable market data and analysis as well as a daily newsfeed, curated by our energy analysts, on the oil, gas, coal and power markets.
This user-friendly tool gives you the essentials about the domestic markets of your concern, including market structure, organisation, actors, projects and business perspectives.
Energy and Climate Databases
Market Analysis