Elevion Group, through its PV and battery storage subsidiary BELECTRIC, has been contracted by ENERTRAG and Enlight Renewable Energy as general balance of plant (GBoP) partner for the 200 MW/840 MWh Bertikow BESS project in Brandenburg, Germany (BELECTRIC press release, 16/10/2026). Commissioning is expected in the first half of 2028.
Bertikow is a standalone lithium iron phosphate (LFP) battery system that will participate in Germany’s energy and ancillary services markets. BELECTRIC’s scope covers civil and electrical infrastructure up to the 33 kV medium-voltage level, including roads and earthworks, foundations, cabling and on-site interface management. It also covers archaeological monitoring and environmental mitigation measures.
Initial construction activities have started. The investment value, the ownership split between ENERTRAG and Enlight, and the battery supplier were not disclosed.